New Water Installations – Meter Only

METER ONLY* WATER METER (≤ 2”) INSTALLATIONS

CLERMONT COUNTY

WATER RESOURCES DEPARTMENT

 

Upon filing a completed application at Permit Central for new water service and after approval of the application, the following steps will need to be taken by the owner/owner’s agent:

 

 

 

You must call to schedule your meter installation with the Water Resources Department (WRD) at 513-732-7970 – Please indicate “Meter Only*”.

*Meter Only indicates WRD crews are installing only the water meter.  The water service line, water meter pit, lid and appurtenances are installed by the private contractor/developer.  This is applicable to all water main extensions / subdivisions approved on or after February 1, 2021.

Note – if meter pit installation is unacceptable, the Water Resources Department will not install the water meter.  The Contractor/Developer must make the necessary repairs.

 

Billing for service will start after the meter is installed.

 

    Last updated December 23, 2020